Project Archive

Includes selected Major Capital Improvement projects recently completed.
Project Name | Phase | Construction Start | Construction End | Total Project Cost |
---|---|---|---|---|
CHS B-Level GMP Facility | Sep 2021 |
Oct 2024 |
$28,650,000 | |
|
||||
CHS South Tower Post-Occupancy Improvements (Floors 2-7) Phase 2 Labs | Jul 2019 |
Feb 2021 |
$33,494,000 | |
|
||||
Gayley Heights | Mar 2019 |
Jun 2022 |
$183,068,000 | |
|
||||
LaKretz Botany Building Renovation | Feb 2019 |
May 2022 |
$36,350,000 | |
|
||||
MP100 Suite 700 Clinic Renovation | Feb 2020 |
Jul 2023 |
$13,625,000 | |
|
||||
Nimoy Theater Renovation | Oct 2021 |
Mar 2024 |
$18,300,000 | |
|
||||
Olympic and Centennial Hall | Jun 2019 |
Nov 2021 |
$222,645,000 | |
|
||||
Powell Library Seismic Improvements Phase 1 | Sep 2022 |
Oct 2024 |
$17,000,000 | |
|
||||
Public Affairs Building Seismic Improvements | Feb 2021 |
May 2023 |
$28,548,000 | |
|
||||
Rosenfeld Hall Expansion and Renovation | Jan 2021 |
Sep 2023 |
$24,000,000 | |
|
||||
Southwest Campus Apartments | Jun 2018 |
Jul 2022 |
$348,000,000 | |
|